POPP5013_2021_501: POPP5013_2021_501 Project Management

Assignment 1

Report: MASH Safeguarding Hub to Safeguard Vulnerable Children & Young Adults

P17056400

.

Word Count: 3308

.

Executive Summary

    Multi-Agency Safeguarding Hubs (MASH) offer a single-point of contact for service users of multiple different services that must liaise with one another to deliver the essential services required to meet their customers’ needs; the Care Act 2014 sets out requirements on the ways in which multiple agencies can share information with one another about their service users and to define and promote well-being (GOV.UK, 2014). By developing centralised hubs for organisations to coexist with one another for the purpose of sharing information with one another to promote wellbeing and to ensure key support activities are carried out in a timely manner by organisations who receive data previously hindered by delays in transmission in an effort to rapidly safeguard those most in need (SCIE, 2014). MASH also enable a centralised point of contact for referees, ensuring a streamlined process for external organisations to be able to simplify the referrals they make (Nottinghamshire Council, n.d.) where such agencies may be unable to determine which organisation is most suitable to receive the referral and perhaps further complicated where more than one referral may be suitable, for example a child who has suffered abuse at the hands of their parents whilst also suffering from drug addiction may require a referral to both child protection services and drug and alcohol treatment services, in this case, only one referral would be needed and the receiver of such referral could then direct the customer to the relevant services allowing the two services to liaise collectively and agree an appropriate support package for the child (Home Office, 2014).

    Developing MASH features complex operations and logistics, including new office space requirements, staffing and other resources, as well as the movement of equipment and consideration for relevant statutory instruments, including the Care Act 2014, Data Protection Act 2018 and the co-ordination of multiple external bodies, notably the police, probation services, child and adult social services, health services (and auxiliary health services, like drug and alcohol services, community care providers, etc) and educational services.

Table of Contents

.

Executive Summary    1

Table of Contents    1

Project Context    2

Rationale of Proposed Plan and Choice of Methods    2

Critical Evaluation of Three Project Management Tools    3

PESTLE Analysis    3

Work Breakdown Structure    7

Gantt Chart    8

Conclusion    8

References    9

Appendices    13

Appendix A: Project Proposal    13

Appendix A.1: Property Shortlist    13

Appendix A.2: Budget Allocation & Proposed Floor Plan    16

Appendix B: Pestle Analysis    17

Appendix C: Work Breakdown Structure    20

Appendix C.1: Project Governance Structure    22

Appendix D: Gantt Chart    23

.

Project Context

    The Director of Social Services have presented a task to develop a MASH in the city of Leicester to safeguard vulnerable children and young adults (CYP) involving the co-ordination of key personnel from health, social services, police, probation services and education. This report has been compiled to identify a new base in the city centre including considerations for purposeful refurbishments to accommodate different teams as well as reviewing the logistics of hiring/transferring staff and purchasing/moving equipment to the new site with a time limit of 6 months and an initial budget of £75,000.

    The purpose of this report is to demonstrate realistic project management to achieve the goal of forming a successful multi-agency safeguarding hub with the resources available to project managers undertaking the task outlined above.

Rationale of Proposed Plan and Choice of Methods

    The project proposal (Appendix A) outlines the plan in which the development of MASH is to be undertaken, featuring the identification of office space in line with the budget (considering the per annum lease cost on a single-year basis and realising the initial budget would need to be increased over time to accommodate the renewal of a lease on a yearly basis – it’s likely, however, that the minimum lease term may be greater than one year but this isn’t factored into the proposal and is subject to negotiation in most cases).

    The office space available to lease which has been identified as most appropriate (Appendix A.1) for MASH is contained on the fourth floor of Norwich House.

    The office space was selected because it’s open plan with two partitioned meeting rooms offering privacy when undertaking meetings between key personnel, service evaluations and meetings with customers using the service where it’s appropriate for them to visit the premises. It also features a “good degree of natural lighting” offering cost-saving advantages on utilities as well as access via a lift and stairs allowing MASH to cater for mobility-impaired users and personnel. The property is also easily accessible and in a prominent city centre location.

    The proposed plan (Appendix A.2) is developed with confidentiality in mind where agencies and staff can easily reach one another on the same floor without the need to use phone or email technology whilst on-site. Realistically, there would need to be designated individuals representing each agency associated with the MASH whose operations will be managed elsewhere, at the social services offices, police station, hospitals or community care administration offices or probation services; this will be especially necessary when dealing with complex multi-agency support.

    Budget allocation can be reviewed in Appendix A.2. In short, operations are expected to be hindered either through a shortage of equipment or staff in the initial budget allowed.

Critical Evaluation of Three Project Management Tools

    When developing a MASH, it’s important to consider which project management tools are most appropriate. Such tools include PESTLE analysis to identify external factors likely to impact the success of a given project, a work breakdown schedule (WBS) to assign key responsibilities in the management of the project and a Gantt Chart to determine the project lifestyle and the intended timescale in which tasks should be executed.

PESTLE Analysis

By using a PESTLE Analysis (Appendix B), project managers are able to evaluate the macro-environmental factors that may affect the project’s likelihood of success (Pourmohammadi et al., 2020) and to identify any risks or opportunities to be mitigated or capitalised (Rasheed et al., 2015; Liu et at., 2018). There are many strengths of using a PESTLE Analysis whilst managing a project, notably in the planning phase of the project as it enables project managers to understand the external influences impacting the potential success of the project. By understanding those influences, project managers can determine whether the project is realistic or whether it’s a non-starter and should be discontinued all together without wasting resources unnecessarily by making a futile attempt, alternatively, it allows project managers to adjust their plans to mitigate risks or take advantage of opportunities that may present themselves as the analysis is undertaken.

The PESTLE analysis, however, does have limitations like any other tool and one of these limitations are the disregard for the micro-environment. Whilst a PESTLE analysis considers policitcal, economic, social, technological, legal and environmental factors impacting a project or the organisation at large, it fails to account for the internal culture, ethics, operations, personnel or management style implemented by an organisation. Therefore, a PESTLE analysis may be less effective without the compliments of a SWOT analysis to understand the internal strengths, weaknesses, opportunities and threats that may impact the project or the organisation. By carrying out the two together, project managers will be able to get a clear understanding of both internal and external factors and better plan the project going forward taking care to consider the internal threats especially and recommending actions to more senior agents within an organisation to increase the likelihood of success of the project by minimising those threats.

A PESTLE Analysis (also abbreviated to PEST analysis when legal and environmental impacts are negligible or unaccounted for) affirms the organisations competitive position and allows project managers to determine strategic risk and is most effective when analysis is undertaken from the perspective of an organisation’s resources, competences and capabilities (Sammut-Bonnici & Galea, 2015) and understanding those requisites may be achieved through the use of tools such as Porter’s 5 Forces (Grundy, 2006) which evaluates threats of new entrants to the market who could tender a more suitable project proposal to the client and the power of suppliers which could impact the cost associated with fulfilling the plans already established (Bernardino et al., 2018).

Another limitation is that situations are dynamic. Considering rapid legislative implementations in the UK relating to covid-19, it’s understandable that a PESTLE analysis conducted in the Summer of 2019 would be irrelevant by the same time the following year when the United Kingdom was shunned into a national lockdown resulting in only essential works being permissible by law – various construction projects, for example, were halted resulting from supply chain issues (COIB, n.d.) and this has knock-on effects on refurbishment projects, especially where suppliers of internal furnishings (including retailers like Dunelm and IKEA) have been forced to close due to operating “non-essential” services. Because of how quickly the external environment can develop and change in a short space of time, PESTLE analysis should be revaluated regularly, however, it’s arguable that the analysis has diminishing returns over time as the project nears completion (Sammut-Bonnici & Galea, 2015) as already completed tasks may not be possible to restart once completed or in progress relative to changes in the external environment – in this instance, project managers must “make do” and consider alternative options to mitigate the impacts of external factors which may limit already completed tasks.

When conducting a PESTLE analysis, it’s prudent to consider the future operations of the project beyond the development as some aspects of MASH may be less appropriate to consider in relation to development alone. Therefore, from a project management point of view, the limitations mean a PESTLE analysis may not always be possible in the entirety and project managers may feel PEST analysis is more appropriate.

Political

    It has been recognised that the overall health of the population improves under left-wing political parties, especially amongst those of a disadvantaged background and BAME groups (Barnish, Tørnes and Nelson-Horne, 2018) because of the impacts of welfare-state generosity being greater under socialist-leaning parties (Qureshi, 2002; Daly, 2011). Whilst the current Conservative government has routinely pledged greater funding for the NHS, critics have indicated the funding is insufficient in real terms considering inflation; funding is further expended by the increased reliance on private sector health services integrating with publicly funded organisations (Wilkinson, 2015).

Funding limitations could impact MASH where services are required by organisations that are unable to afford to provide adequate services to customers who must be prioritised.    

Economic

    As the economy falters from the fall out of national lockdowns for large proportions of the year 2020 and with restrictions likely to be in place until way into 2021, the government funded budgets made available to local authorities and by extension services such as multi-agency safeguarding hubs are likely to be limited due to decreased tax revenues earned by the government increasing the likelihood of austerity measures being introduced (Hargreaves, 2020), this is evident through the impacts of austerity measures implemented resulting from the financial crisis of 2008 (Ginn, 2013) with exacerbations varying from region to region across the UK (Gray & Barford, 2018).

    The closure of probation services due to budget cuts resulting from austerity means young offenders have to travel further for support, oftentimes youth offending orders are reduced to occasional face to face appointments supported by telephone meetings which are inadequate for the purposes of supervising young offenders during their rehabilitation process (Walker, Annison & Beckett, 2019) with youth offending steadily declining between 1995-2005 before resurging from 2008 onwards (Griffiths & Norris, 2019).

Social

    Customers may feel uneasy about data being shared between organisations or the application of safeguarding measures such as breaching confidentiality rights to report child abuse or sexual exploitation or where “the law does not prevent the sharing of sensitive, personal information between organisations where the public interest served outweighs the public interest served by protecting confidentiality – for example, where a serious crime may be prevented” (SCIE, 2014). This could result in customers being less likely to accept referrals being made on their behalf or be less forthcoming with information where an employee cannot assure confidentiality which poses a risk of inadequate support being offered to the customer.

    Resentment for involuntary services, such as custodial detentions facilitated by police arrests and child protection activities carried out social services which may see children temporarily or permanently placed into the care sector, is well documented in a range of reports and statistics, especially amongst more disadvantaged communities including those of a low-income (Smith et al., 2011) and black and minority ethnic communities (BAME) who experience police interactions, including stop and search, more frequently than white ethnic groups (Barrett, Fletcher & Patel, 2013).

    Balancing the interests of agencies involved in MASH can be difficult, where the police will prioritise victims through the use of policing activities (e.g. arresting perpetrators of crime), social services will typically want to take direct action to safeguard those at risk such as placing them in the care of somebody else (Ford et al., 2019).

    The population of over-85’s has risen by over 20% since 2010 (The Health Foundation, 2019), with it the cost of providing state-funded care to the elderly has increased respectively, this places greater strain on MASH to cope with the increasing elderly population whilst still providing the same level of service to younger population groups. It may be that designated personnel will be required to deal primarily with older populations to keep services operating efficiently without exceeding capacity.

Technological

    The use of technology in the social care sector and in other primary services including law enforcement has allowed employees to reduce the amount of man-hours they have to dedicate to a task to complete it, for example, advancements in wireless technology has allowed the average cost to fall significantly making it more accessible to employees, this means they’re able to avoid having to return to an office to compile and send reports or access customer relationship management (CRM) records increasing overall efficiency and reducing the amount of wasted hours travelling throughout a working day – this results in being able to service more customers and dedicate more resources to providing the support customers need (Ramsey & Montgomery, 2014).

    Technology has also benefited the education sector and is used routinely in classrooms, from interactive whiteboards replacing overhead projectors to integrating libraries and websites so students can easily check what books are available and even to reserve them (Bond, Zawacki-Richter & Nichols, 2018); when considering the use of education in criminal rehabilitation, it could be wise to integrate probation and educational services through the use of technology since education is one of the most effective forms of reducing reoffending (McMahon & Jump, 2017). Using technology, probation services can monitor offender’s progression throughout their academic career and could pose to be a beneficial alternative to punitive measures imposed on many ex-offenders (Noguera, 2003).

    With the use of any technology, the risk of interference is always present from hackers and data breaches to interception of communications and sabotage (Teymouri and Ashoori, 2011); when risks present themselves in MASH environments, it’s especially important to mitigate them so as to protect vulnerable service users; a technologically savvy yet abusive ex-husband, for example, may attempt to infiltrate a network to intercept communications relating to the safeguarding of his estranged ex-wife who fled the marriage due to domestic violence (College of Policing, 2020).

Legal

    Considering the risk of data breaches, the Data Protection Act 2018 affords a financial risk under the General Data Protection Regulations (GDPR) where data breaches can result in large fines being levied on organisations. It’sn’t uncommon for data breaches to occur, but the severity of most data breaches is low. For MASH, who will be dealing with vulnerable customers, the severity of any data breach is likely to be greater than other organisations. For example, if contact details of elderly cohorts were intercepted, the likelihood of them falling victim to certain types of scams are greater than those who’re younger (James, Boyle & Bennett, 2014).

    The Care Act 2014 offers complex regulations governing the sharing of data between organisations and which individuals within an organisation has access to sensitive information (Vezyridis & Timmons, 2017); without adequate systems in place to train staff, it could be reasonably easy to fall foul of the legislation which could lead to direct, criminal prosecution of the individual who breached the guidelines, as well as those who may have been negligent if adequate training hasn’t been provided, action taken against organisations including de-registration of any authorisations/licenses to operate or civil action taken by individuals seeking compensation from organisations resulting from a breach (Schwehr, 2019).

Environmental

    There are few environmental factors that have high-impact on the development of MASH however, in terms of MASH operations, for individual customers, environmental factors do exist – especially when considering their health. Pollution in an environment is more likely to affect those in less economically-developed areas and lower income backgrounds whilst cold weather in Winter is likely to negatively impact older populations – all of these must be considered when developing safeguarding plans.

Work Breakdown Structure

    A Work Breakdown Structure (WBS) (Appendix C) can be used to define key tasks into manageable sections allowing managers to estimate costs depending on each task and increase the overall efficiency of completing a project – by visualising a project in a WBS, project managers can eliminate less important tasks or dedicate more resources to tasks with greater importance (Cerezo-Narváezet al., 2020); good resource allocation is crucial for complex, budget-constrained tasks (Scott & Jefferson, 1995).

    One of the benefits of WBS when factoring in the use of public funds like developing MASH is that they can be integrated into Cost Breakdown Structures (CBS), allowing project managers to conceptualise costs and maintain budgets without deviating from one tool to another (Cerezo-Narváezet al., 2020), in other words, a CBS can be used as an overlay to WBS.

    A WBS also offers individuals taking part in a project an opportunity to better understand the hierarchy governing the project and who is responsible for what aspect of the project – a Project Governance Structure (PGS) (Appendix C.1) can be defined from the WBS offering a more thoroughly developed Gantt chart (Childre & Perce, 1998). A PGS becomes especially useful in MASH as one agency may need to understand who their key service managers are and what other agencies, they’re responsible where complex issues arise where a course of action cannot be easily agreed between the agencies involved.

    A limitation of WBS is that it provides no chronology without defining a specific schedule; project managers may expend too much or too little time on a given task without necessary prioritisations.

Gantt Chart

    A GANT Chart (Appendix D) determines the project schedule (Geraldi & Lechter, 2012) and the time expected to undertake each task in the project lifestyle, it works well with the WBS because it offers time-relative constraints based on a given activity, including how much time a given task should take and when the task should be undertaken. This is beneficial because it minimises the risk of an individual being overwhelmed with the number of tasks needed to be carried out for the project to be a success, in other words, it allows an individual to pace themselves realising that whilst significant responsible is burdened by them, the tasks they must undertake may not fall immediately due for completion, instead they may need to rely on other individuals completing their workload before they can maintain their own responsibilities.

    On the other hand, by relying on other key steps of the Gantt chart to be fulfilled before an individual can continue their responsibilities determined by the WBS may result in catastrophe if another element of the Gantt chart is delayed or fails to be completed. It’s prudent, therefore, for other operatives within the project to use resources wisely and expect a likelihood of needing to divert these resources (Caughron & Mumford, 2008), whether it’s tangible resources like equipment or manpower or intangible resources like consultative support to facilitate the completion of other tasks that are crucial to the success of future tasks.

    The benefit of a Gantt chart is that it allows a project manager to clearly define a schedule for a given task, allowing the prioritisation of tasks based on allocated time available to complete the project. Unlike a WBS, it doesn’t offer an ability for a project manager to monitor costs, but it may, however, allow the project manager to delegate tasks to others involved – this is important when developing MASH because the project itself is quite complex.

    Gantt charts should not be used alone as they fail to define how much work is involved in a task (Geraldi & Lechter, 2012), it’s sensible to use a Gantt chart to complement another tool, such as WBS.

    Similarly, a WBS is a good compliment of a Gantt charge when addressing another limitation of the tool in that they can become very complex in a short space of time, without defining resource allocation. Alone, projects can become unmanageable (Wilson, 2003).

Conclusion

    The development of MASH is a complex project requiring multiple tools to complete within budget. Whilst the proposal means budgets are exceeded or operational inefficiencies arise, it highlights the crucial activity of effective project management – without adequate planning, budget excesses may be unforeseen and where further budget allocation is impossible, the project would fail wasting resources already expended up until the point the budget is expended. By using the tools mentioned throughout this report, project managers can assess the overall viability of a project in terms of budget and resource allocation and therefore determine the likelihood of success and set realistic expectations for those involved.

References

Barnish, M., Tørnes, M. and Nelson-Horne, B., 2018. How much evidence is there that political factors are related to population health outcomes? An internationally comparative systematic review. BMJ Open, 8(10), p.e020886.

Barrett, G., Fletcher, S. and Patel, T., 2013. Black minority ethnic communities and levels of satisfaction with policing: Findings from a study in the north of England. Criminology & Criminal Justice, 14(2), pp.196-215.

Bernardino, E., Serona, K., Cando, J., Acosta, I. and Malagapo, E., 2018. Strengthening Success Factors and Overcoming Profitability Barriers towards Sustainable Project Management Consultant Companies. Business and Economic Research, 8(2), p.230.

Blueprint CPD. n.d. Work Breakdown Structure – Benefits & Challenges. [online] Available at: <https://www.blueprintcpd.com.au/blog/the-benefits-and-challenges-of-work-breakdown-structure-wbs> [Accessed 15 January 2021].

Bond, M., Zawacki-Richter, O. and Nichols, M., 2018. Revisiting five decades of educational technology research: A content and authorship analysis of the British Journal of Educational Technology. British Journal of Educational Technology, 50(1), pp.12-63.

Butler, P., 2018. Social Care Needs For Over-85S Predicted To Double In Next 20 Years. [online] the Guardian. Available at: <https://www.theguardian.com/society/2018/aug/30/social-care-needs-for-over-85s-predicted-to-double-in-next-20-years#:~:text=2%20years%20old-,Social%20care%20needs%20for%20over%2D85s%20predicted,double%20in%20next%2020%20years&text=a%20new%20study.-,Overall%2C%20more%20than%201%20million%20people%20aged%2065%20or%20over,with%20multiple%20long%2Dterm%20conditions.> [Accessed 12 January 2021].

Caughron, J. and Mumford, M., 2008. Project Planning: The Effects of Using Formal Planning Techniques on Creative Problem-Solving. Creativity and Innovation Management, 17(3), pp.204-215.

Cerezo-Narváez, A., Pastor-Fernández, A., Otero-Mateo, M. and Ballesteros-Pérez, P., 2020. Integration of Cost and Work Breakdown Structures in the Management of Construction Projects. Applied Sciences, 10(4), p.1386.

Childre, F. and Perce, K., 1998. Project Management Skills. AAOHN Journal, 46(8), pp.391-405.

CIOB. n.d. Coronavirus Impact On Construction. [online] Available at: <https://www.ciob.org/coronavirus-impact-construction> [Accessed 12 January 2021].

College of Policing, 2020. 2020. Risk And Vulnerability. [online] Available at: <https://www.app.college.police.uk/app-content/major-investigation-and-public-protection/domestic-abuse/risk-and-vulnerability/> [Accessed 12 January 2021].

Crawford, L. and Helm, J., 2009. Government and Governance: The Value of Project Management in the Public Sector. Project Management Journal, 40(1), pp.73-87.

Daly, M., 2010. Shifts in family policy in the UK under New Labour. Journal of European Social Policy, 20(5), pp.433-443.

Ford, K., Newbury, A., Meredith, Z., Evans, J., Hughes, K., Roderick, J., Davies, A. and Bellis, M., 2019. Understanding the outcome of police safeguarding notifications to social services in South Wales. The Police Journal: Theory, Practice and Principles, 93(2), pp.87-108.

Geraldi, J. and Lechter, T., 2012. Gantt charts revisited. International Journal of Managing Projects in Business, 5(4), pp.578-594.

Ginn, J. (2013). Austerity and Inequality. Exploring the Impact of Cuts in the UK by Gender and age. Research on Ageing and Social Policy, 1(1), 28-53.

Globerson, S., 1994. Impact of various work-breakdown structures on project conceptualization. International Journal of Project Management, 12(3), pp.165-171.

GOV.UK. 2014. Care And Support Statutory Guidance. [online] Available at: <https://www.gov.uk/government/publications/care-act-statutory-guidance/care-and-support-statutory-guidance> [Accessed 12 January 2021].

GOV.UK. 2014. Working Together To Safeguard Children: Multi-Agency Safeguarding Hubs. [online] Available at: <https://www.gov.uk/government/news/working-together-to-safeguard-children-multi-agency-safeguarding-hubs> [Accessed 11 January 2021].

Gray, M. and Barford, A., 2018. The depths of the cuts: the uneven geography of local government austerity. Cambridge Journal of Regions, Economy and Society, 11(3), pp.541-563.

Griffiths, G. and Norris, G., 2019. Explaining the crime drop: contributions to declining crime rates from youth cohorts since 2005. Crime, Law and Social Change, 73(1), pp.25-53.

Grundy, T., 2006. Rethinking and reinventing Michael Porter’s five forces model. Strategic Change, 15(5), pp.213-229.

Hargreaves, A., 2020. Austerity and inequality; or prosperity for all? Educational policy directions beyond the pandemic. Educational Research for Policy and Practice,.

The Health Foundation. 2019. The Current Political Impasse Around Social Care Funding Is Having Serious Human Consequences | The Health Foundation. [online] Available at: <https://www.health.org.uk/news-and-comment/news/the-current-political-impasse-around-social-care-funding-is-having-serious-human-consequences> [Accessed 12 January 2021].

Home Office, 2014. Multi Agency Working And Information Sharing Project: Final Report. [online] HM Government. Available at: <https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/338875/MASH.pdf> [Accessed 11 January 2021].

James, B., Boyle, P. and Bennett, D., 2014. Correlates of Susceptibility to Scams in Older Adults Without Dementia. Journal of Elder Abuse & Neglect, 26(2), pp.107-122.

Liu, Y., Sun, C., Xia, B., Liu, S. and Skitmore, M., 2018. Identification of Risk Factors Affecting PPP Waste-to-Energy Incineration Projects in China: A Multiple Case Study. Advances in Civil Engineering, 2018, pp.1-16.

Lock, D., 2013. Project Management. 10th ed. Farnham: Gower Publishing.

Madauss, B., 1984. Management Advantages of the Standard Work Breakdown Structure for European Satellite Projects. Journal of Parametrics, 4(2), pp.42-50.

Maylor, H., 2010. Project Management. 4th ed. Harlow: Financial Times Prentice Hall.

McMahon, G. and Jump, D., 2017. Starting to Stop: Young Offenders’ Desistance from Crime. Youth Justice, 18(1), pp.3-17.

Miranda, S. and Helia, V., 2019. Project Schedule Evaluation Using Project Manegement Software: A Case Study in an Electric Steam Power Plant in Indonesia. IOP Conference Series: Materials Science and Engineering, 598, p.012075.

Noguera, P., 2003. Schools, Prisons, and Social Implications of Punishment: Rethinking Disciplinary Practices. Theory Into Practice, 42(4), pp.341-350.

Nottinghamshire Council, n.d. Multi-Agency Safeguarding Hub (MASH). [online] Nottinghamshire County Council. Available at: <https://www.nottinghamshire.gov.uk/care/childrens-social-care/nottinghamshire-children-and-families-alliance/pathway-to-provision/multi-agency-safeguarding-hub-mash> [Accessed 12 January 2021].

Planview. n.d. What Is Work Breakdown Structure? | Planview Leankit. [online] Available at: <https://www.planview.com/resources/articles/work-breakdown-structure/#:~:text=The%20work%20breakdown%20structure%20divides,allotted%20for%20the%20entire%20project.> [Accessed 12 January 2021].

Pourmohammadi, K., Bastani, P., Shojaei, P., Hatam, N. and Salehi, A., 2020. A comprehensive environmental scanning and strategic analysis of Iranian Public Hospitals: a prospective approach. BMC Research Notes, 13(1).

Ramsey, A. and Montgomery, K., 2014. Technology-Based Interventions in Social Work Practice: A Systematic Review of Mental Health Interventions. Social Work in Health Care, 53(9), pp.883-899.

Rasheed, S., Wang, C., Yaqub, F. and Memon, S., 2015. Risk leveling in business environments – A novel approach for macro risk management. Journal of Industrial Engineering and Management, 8(3).

Reddy, C., 2019. Work Breakdown Structure: Advantages And Disadvantages – Wisestep. [online] WiseStep. Available at: <https://content.wisestep.com/work-breakdown-structure-advantages-disadvantages/> [Accessed 12 January 2021].

Sammut-Bonnici, T. and Galea, D., 2015. PEST analysis. Wiley Encyclopedia of Management, pp.1-1.

Schwehr, B., 2019. Why Councils Risk Payouts By Failing To Meet Care Act Duties – Community Care. [online] Community Care. Available at: <https://www.communitycare.co.uk/2019/12/04/councils-risk-payouts-failing-meet-care-act-duties/> [Accessed 12 January 2021].

SCIE, 2014. Self-Neglect Policy And Practice: Building An Evidence Base For Adult Social Care. [online] Social Care Institute for Excellence (SCIE). Available at: <https://www.scie.org.uk/self-neglect/policy-practice/evidence-base> [Accessed 12 January 2021].

Scott, C. and Jefferson, T., 1995. Allocation of resources in project management. International Journal of Systems Science, 26(2), pp.413-420.

Smith, M., Gallagher, M., Wosu, H., Stewart, J., Cree, V., Hunter, S., Evans, S., Montgomery, C., Holiday, S. and Wilkinson, H., 2011. Engaging with Involuntary Service Users in Social Work: Findings from a Knowledge Exchange Project. British Journal of Social Work, 42(8), pp.1460-1477.

Startups.co.uk. n.d. What Costs You’ll Need To Consider For Commercial Premises. [online] Available at: <https://startups.co.uk/premises/commercial-buildings/what-costs-youll-need-to-consider-for-commercial-premises/> [Accessed 15 January 2021].

Teymouri, M. and Ashoori, M., 2011. The impact of information technology on risk management. Procedia Computer Science, 3, pp.1602-1608.

Qureshi, H., 2002. Social and Political Influences on Services for Older People in the United Kingdom in the Late 20th Century. The Journals of Gerontology Series A: Biological Sciences and Medical Sciences, 57(11), pp.M705-M711.

Vezyridis, P. and Timmons, S., 2017. Understanding the care.data conundrum: New information flows for economic growth. Big Data & Society, 4(1), p.205395171668849.

Walker, S., Annison, J. and Beckett, S., 2019. Transforming Rehabilitation: The impact of austerity and privatisation on day-to-day cultures and working practices in ‘probation’. Probation Journal, 66(1), pp.113-130.

Wilkinson, E., 2015. The NHS: what are the UK’s political parties promising?. The Lancet, 385(9973), pp.1059-1062.

Wilson, J., 2003. Gantt charts: A centenary appreciation. European Journal of Operational Research, 149(2), pp.430-437.

Appendices

Appendix A: Project Proposal

Appendix A.1: Property Shortlist

Leicester Marketplace Open Plan Office

2120sqft – £12500 p/a

.

https://www.zoopla.co.uk/to-rent/commercial/details/53274101?search_identifier=21846530ea7f9d43b3640efc137107e4

Fusion Recruitment Agency on Belvoir Street

1476sqft – £13000p/a

https://www.zoopla.co.uk/to-rent/commercial/details/57082571?search_identifier=e2bbe0d812360637cfccee03147d4dff

Norwich House Open Plan Office, Horsefair Street, Leicester City Centre

Image captured from PrimeLocation (a Zoopla owned brand) and features the inside of the property advertised above.

1995sqft – £19000 p/a

https://www.zoopla.co.uk/to-rent/commercial/details/55957190?search_identifier=97d54badd88910af34bf12315f2f43f2

Appendix A.2: Budget Allocation & Proposed Floor Plan

    The most appropriate property selected would be Norwich House Open Plan Office, Horsefair Street, Leicester City Centre. This is because it offers a wide, open-plan area which can be readily adapted to suit the needs of MASH as defined in the proposed floor plan below.

    The floor plan above demonstrates an effective layout offering privacy and functionality, where each agency of MASH can interact with one another whilst offering space to service customers and other external agencies.

    Highlighted in green, numbered 1-4 are individual offices built with party walls, each with lockable doors allowing agencies to prevent unauthorised/unintended sharing of data with other agencies. They would be assigned to agencies involved in MASH and can be adapted to accommodate different agencies where necessary. The justification for this is that the agencies involved in MASH will be employed externally, by the police force, probation services, educational bodies and so on rather than MASH.

    The blue area shows reception desks, allowing multiple customers to be served by receptionists at a given time. These desks can also be used by administrative staff making outbound calls, responding to emails and dealing with referrals as a first point of contact. The staff members concerned with this would be directly employed by MASH and therefore budgets would need to be considered. Just two staff members employed on minimum wage would cost upwards of £31,740 which, after lease costs, would leave less than £25,000 in the budget to cover the cost of refurbishment, equipment acquisition, recruitment costs (hiring activities, pensions, etc), marketing, staff training, utilities and logistics. These activities would be expected to cost approximately £23,460 per annum based on average monthly office running costs (Startups.co.uk, n.d.) disregarding lease and staff costs as these have already been accounted for.

    Finally, the black outline identifies amenities already in place within the building with the two offices flanking the door being assumed locations as their location is not divulged in the property listing. The floor plan also offers seating area for customers and visitors waiting to be served identified by yellow dashes.

Therefore, hiring two full-time staff members, running costs and lease costs equate to £74,200 which leaves £800 for equipment acquisition and other costs associated with completing the project. It’s unrealistic to expect refurbishment costs and equipment costs will fall within this budget and therefore, either more money will be required or the office may have to reduce staff to a single full-time employed staff member offering a further £15,870 to the budget to complete the project – it’s reasonable to expect, with an added £15,870 that these costs should be readily covered though by only hiring one staff member instead of two, operational efficiency will be significantly lower and issues will arise if an employee wishes to take time off for illness or leisure.

.

Appendix B: Pestle Analysis

Classification

Point

Implication

Opportunity or Threat

Political

Political parties influence overall health of population

Left-wing parties typically promote increased overall health across all social classes, particularly those from disadvantaged and minority ethnic backgrounds

Opportunity when governed by left-leaning parties. Threat when governed by right-leaning parties.

Political

Increased government funding of NHS and social care has had limited positive impact

In real terms, considering inflation and increased costs due to growing population, increased government funding has failed to stabilise crisis-stricken public services

Threat. High level.

Political

Services still underfunded despite increased budgets.

Underfunded services may fail to deliver adequate service provisions to those most in need.

Threat. High level.

Economic

Coronavirus measures have put strain on the economy which are likely to result in austerity measures (Hargreaves, 2020)

Budget cuts for MASH and primary and secondary services required to efficiently operate MASH.

.

Threat. High level.

Economic

Coronavirus measures have put strain on the economy which are likely to result in austerity measures (Hargreaves, 2020)

Increased likelihood of complications arising from being unable to deliver core services adequately to those most in need, including youth reoffending

Threat. High level.

Social

.

Customers may not appreciate or want data to be shared between organisations despite the legal duty of care to so

Customers may be less likely to use or be as honest or forthcoming with the service disabling the ability to provide adequate support to customers

Threat. Moderate

Social

.

Customers may resent the decision to breach the right to confidentiality where the public interest outweighs the customer’s own wishes

Customers may be less likely to use or be as honest or forthcoming with the service disabling the ability to provide adequate support to customers

Threat. Moderate

Social

.

Resentment of involuntary services, including arrests and detention under the mental health act, the removal of children from family homes as part of safeguarding measures, etc.

Customers may refuse to engage with services where involuntary services are provided. This could lead to inadequate support.

Threat. Moderate.

Social

.

Resentment of involuntary services, including arrests and detention under the mental health act, the removal of children from family homes as part of safeguarding measures, etc.

Community may resent services where it’s felt involuntary services are excessive despite being in the customer’s or public’s best interests.

Threat. High level.

Social

.

Resentment of involuntary services, including arrests and detention under the mental health act, the removal of children from family homes as part of safeguarding measures, etc.

Third-parties affected by involuntary services, such as parents of neglected children, may be violent or aggressive towards those undertaking involuntary services

Threat. Severe.

Social

.

Conflicts between external agencies preferred method of operation

Extensive resources expended during the planning of support could become expensive with little productivity, for example, where the social services may prefer to remove a child at risk of harm from an environment immediately, the police may prefer to gather evidence of crime taking place where removing the child may alert any criminals to an investigation limiting the opportunity of conviction and potentially impacting the ability of MASH to safeguard vulnerable people.

Threat. Moderate.

Social

.

Growing population overall, especially cohorts over-85 years old

Growing populations require ever increasing operational budgets and as population groups grow faster than other groups, the demand for resources increases respectively (Butler, 2018)

Threat. Low level.

Technological

More accessible wireless technology

Enables employees to carry out tasks ‘on-the-go’ without the need to return to the office increasing the efficiency of services and allowing them to dedicate more time and resources to actually providing services instead of travelling back to an office for administrative purposes

Opportunity. High level.

Technological

Integration of education and probation services to reduce reoffending

It’s been shown that education has reduced reoffending and if used appropriately could assist probation services in monitoring ex-offenders’ progress remotely

Opportunity. Moderate.

Technological

Risk of interference, data breaches and sabotage

Where technological vulnerabilities exist, there are financial risks from possibility of being fined for data breaches, as well as safety risks when technology is being used to provide services to vulnerable individuals.

Threat. Ongoing. High level.

Legal

Data breaches

Fines from ICO

Threat. Ongoing. High Level.

Legal

Data breaches

Interception of vulnerable customer data which could be used to scam vulnerable people or otherwise abuse the data or carry out unlawful actions

Threat. Ongoing. Severe.

Legal

Complex legislation, Care Act 2014, and lack of adequate training.

Risk of personal prosecution, de-registration or civil action.

Threat. Moderate.

Environmental

Impact of pollution and seasonal changes on customers and services

Pollution can negatively impact the health of customers and seasonal variations of weather (e.g. colder weather and elderly) offer different operational risks

Threat. Negligible from a project management point of view in developing a MASH. Variable from an operations point of view.

.

Appendix C: Work Breakdown Structure

.

Project Manager

Operational Managers

Office (1.1)

Recruitment (2.1)

Service Operations (3.1)

Acquisition (1.2)

Staff (2.2)

Referrals (3.2)

Refurb (1.3)

External Contractors (2.3)

Cleaners (2.3.1)

IT specialists (2.3.2)

Service Providers (3.3)

Kit Out (1.4)

External Contractors (2.3)

Cleaners (2.3.1)

IT specialists (2.3.2)

Service Providers (3.3)

Equipment (1.4.1)

Reception (1.4.1.1)

Meeting Rooms (1.4.1.2)

Other (1.4.1.3)

IT (1.4.2)

External Agencies (2.4)

Probation (2.4.1)

Health (2.4.2)

Education (2.4.3)

Social Services (2.4.4)

Risk Assessments (3.4)

Immediate safeguarding activities (3.4.1)

Non-urgent activities (3.4.2)

.

.

Case Management (3.5)

    The WBS is broken down into individual tasks (numbered) and responsibilities clearly defined (Project Manager/Operational Managers). It begins with assuming the core responsibilities (tasks 1.1, 2.1 and 3.1) before considering the individual elements required to achieve a desirable outcome in each task. For example, for Office (task 1.1), acquiring the office (1.2) is key and a higher priority than refurbishing the office (1.3); without completing 1.2, 1.3 would not be possible, nor would it be ideal to plan any refurbishment activities as this could be wasteful should the office space acquired have desirable amenities. The refurbishment activity can be split into two individual activities associated with kitting out the office space (1.4) once the refurb is complete. These activities are substantial and are therefore separated into two different activities, the first being associated with equipping the office’s individual rooms whilst the second focuses on the IT infrastructure (networks, computers, VOIP systems, CRM and so on).

    Recruitment (2.1) is another core activity and deals with the hiring of employed staff (2.2) and external contractors (2.3) including IT specialists and cleaners – it wouldn’t be appropriate with such a small budget to hire cleaners and IT specialists directly. It also deals with the hiring of external agencies such as the police, probation, etc.

    The final core activity relates to the actual operations of the MASH and would perceivably be most effective upon completion of the project of developing MASH. It is included to allow for a smooth transition between development and operations and by integrating the initial handover from project manager to operational managers, a ‘cliff-edge’ of changes can be avoided. The core activity of operational managers focuses on service operations and managing service providers (including external agencies such as the police, education, probation and health and social care), handling referrals, conducting primary risk assessments (individual agencies may conduct their own secondary risk assessments), undertaking urgent and non-urgent safeguarding activities and managing cases for the duration in which a customer requires the use of the services provided by MASH.

Appendix C.1: Project Governance Structure

^ Not to be confused with Work Breakdown Structure (used to develop the foundations in whch the project governance structure can operate)

Appendix D: Gantt Chart

Activity (see WBS)

Month 1

Month 2

Month 3

Month 4

Month 5

Month 6

1.1

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

1.2

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

1.3

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

1.4

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

2.1

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

2.2

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

2.3

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

2.4

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

Wind Down

/

Handover

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

Service Operations

(Ongoing)

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

    The Gantt chart defines a schedule in which the project is to be completed. Using the WBS, it is possible to plot each core activity and the activity required to complete the core activity relevant to the set schedule of 6 months.

    The Office (1.1) activities are expected to take 2.5 months, identified in the first section labelled 1.1, however the actual acquisition of the office (1.2) is due to take only one month, this is allowing time for premises to be located, contracts drawn up, relevant vetting processes required prior to tenanting the premises and so on.

    Once the acquisition has been formalised, the premises needs to be refurbished (1.3) and this takes place from the point contracts have been signed through to the third quadrant of month two. As the premises is refurbished, kitting the premises out with relevant equipment and IT can take place, this is why the kit out (1.4) starts from the second quadrant of month two overlapping 1.3 – as one area is completed, desks, telephones and so on can be moved into that area.

    Similarly, when areas of the office are completed, the second core activity, recruitment (2.1) can be undertaken. This activity overlaps the first so as to allow time for recruitment which needn’t wait until the kit out is complete and minimises the amount of time between the first activity being completed and the time in which staff can start work.

    The activity of recruiting begins before staff are hired (2.2) and the hiring stage begins in the first quadrant of month four ends in the second quadrant of month six, this is because staff aren’t actually required to start work until the final stages of the project near completion. In that time, staff training takes place and further recruitment activities are undertaken, such as recruiting external contractors (2.3) like cleaners who are hired before employed staff so as to assist with cleaning up as refurbishments take place.

    External agencies (2.4) including police, probation and social services, etc are hired on an ongoing basis, it is likely different individuals from each service will be appointed to deal with different specialisms, for example, a child sexual abuse victim will be dealt with by officers and social workers with different skillsets then an elderly hospital leaver, as would an alcoholic adult with a propensity for petty crime need different support to a victim of human trafficking, and so on.

    Finally, as the project nears completion, the wind-down and handover process can begin. This is where MASH begins operating. The wind-down process is due to begin in the second quadrant of the final month with handover taking place shortly after with the two activities of handover and service operations overlapping one another to reduce friction and allow project managers to offer support during the handover phase to operational managers to avoid issues further down the line, if an operations manager doesn’t understand why certain aspects of the project have been carried out in such a way, for example, this would be the moment in which to seek clarity. It is important to offer this handover phase so as to avoid further expense of time and cost by having to revert back to the project managers for further advise and guidance. It goes without saying, however, that over time, operational managers will find their own way of doing things and less crucial aspects of the project as it was developed will change to suit the operational manager’s style of management and operations.